城市轨道交通全自动运行系统综合联调方案
蒋勇
Integrated Joint Commissioning Scheme of Urban Rail Transit FAO System
JIANG Yong
-
作者信息:上海申通轨道交通研究咨询有限公司, 200070, 上海
-
Affiliation:Shanghai Shentong Rail Transit Research & Consultancy Co., Ltd., 200070, Shanghai, China
-
关键词:
-
Key words:
-
DOI:10.16037/j.1007-869x.2023.02.028
-
中图分类号/CLCN:U29-39;U211.8
-
栏目/Col:应用技术
摘要:
结合南宁轨道交通5号线一期工程,探索了FAO(全自动运行)系统综合联调的技术路线,重点研究了基于FAO场景的功能验证方案,提出了功能验证与场景验证相结合的方法,并对功能验证过程中的常见问题进行分析并提出解决方案。
Abstracts:
Based on the phase I project of Nanning Rail Transit Line 5, the technical route of FAO (fully automatic operation) system integrated joint commissioning is explored. The function trial scheme based on FAO scenario is emphatically studied, and the combined method of function trial and scenario verification is proposed. Common problems from function trial process are analyzed and solutions are proposed.