轨道交通信号系统升级改造期间新旧系统倒接方式及应用分析*
李立明1李建光2顾家泉3柴晓冬1郑树彬1陈兴杰1
Analysis of the Application and Reverse Connection Methods Between the Rail Transit Signal New and Old Systems During Upgrading
LI LimingLI JianguangGU JiaquanCHAI XiaodongZHENG ShubinCHEN Xingjie
-
作者信息:1.上海工程技术大学城市轨道交通学院,201620,上海;
2.中铁三局集团有限公司,030001,太原;
3.上海地铁维护保障有限公司通号分公司,200235,上海
-
Affiliation:College of Urban Railway Transportation, Shanghai University of Engineering Science, 201620, Shanghai, China
-
关键词:
-
Key words:
-
DOI:10.16037/j.1007-869x.2020.09.006
-
中图分类号/CLCN:U231.7;U282+.5
-
栏目/Col:研究报告
摘要:
在轨道交通信号系统升级改造施工调试期间,新旧系统需进行多次倒接。结合上海轨道交通5号线工程应用实例,详细介绍不同倒接方式的设计原理、施工方案及倒接操作方法。对不同倒接方式的适用范围、经济性、可靠性及可维护性进行分析比较,供其他同类工程参考借鉴。
Abstracts:
During the construction and commissioning of the rail transit signal system upgrading, multiple reverse connections between the new and old systems are required. Combined with the practical application of reverse connection on Shanghai metro Line 5, the design principle, construction scheme and operation method of different reverse connection methods are introduced in detail. The application range, economy, reliability and maintainability of different reverse connectionsare analyzed and compared, providing reference for projects in the same category.