苏州轨道交通1—4号线主变电所故障情况下供电方式调整策略

黄吕昊

Power Supply Adjustment Strategy in the Event of Suzhou Rail Transit Line 1-Line 4 Main Substation Failure

HUANG Lyuhao
摘要:
介绍了苏州轨道交通1—4号线主变电所的设置现状。模拟分析了单个主变电所故障退出对各线路供电的影响及相应的供电方式调整策略。提出了主变电所故障情况下线网供电方式调整的原则,并总结了供电方式调整时的注意事项。对比分析了各种调整策略的优缺点,并给出了选择条件。
Abstracts:
Suzhou Rail Transit Line 1-Line 4 main substation set-up situation is introduced. The influence of failure exit of a single main substation on power supply of each line and the correspondent power supply adjustment strategy is simulated and analyzed. The principle of line network power supply mode adjustment under condition of main substation failure is proposed. Key items in power supply mode adjustment that require attention is summarized. The advantages and disadvantages of various adjustment strategy are compared and analyzed, and the choice conditions are given.
引文 / Ref:
黄吕昊. 苏州轨道交通1—4号线主变电所故障情况下供电方式调整策略. 城市轨道交通研究, 2022, 25(5): 105.
HUANG Lyuhao. Power supply Adjustment Strategy in the Event of Suzhou Rail Transit Line 1-Line 4 Main Substation Failure. Urban Mass Transit, 2022, 25(5): 105.
论文检索