Abstract:
In order to promote energy conservation and strengthen green construction management during shield construction, a section shield tunnel project between Yufuhe Station and Wangfuzhuang Station on Jinan rail transit Line 1 taken as the research object, the typical stratum parameters, construction parameters, energy and material consumption in shield tunneling and segment installation are statistically analyzed. The correlations between the consumption of energy and material and the stratum factors plus shield construction parameters are summarized, in order to provided reference for green shield construction in other projects.