新建换乘通道密贴下穿既有地铁车站施工工序优化

Optimization of Construction Procedure of Newly\|built Transfer Passage Closely Under passing Existing Metro Station

  • 摘要: 依托新建换乘通道密贴下穿既有地铁车站工程,针对新建换乘通道采用多分部开挖的施工工序难题,采用数值模拟对比分析了3种不同施工工序引起的既有地铁车站、新建换乘通道、围岩介质等的力学响应。结果表明:从既有地铁车站底板附加变形、新建换乘通道初期支护变形及围岩塑性区指标来看,工况1所引起的最大变形值及塑性区体积均相对最小,建议采用工况1为优选施工工序。

     

    Abstract: Taking the project of the newly built transfer passage closely under\|passing existing metro station as the background, targeting the construction procedure challenge caused by the newly\|built transfer passage adopting multi\|division excavation, the mechanical responses of existing metro station, newly\|built transfer passage, surrounding rock medium caused by three different excavation procedures are compared and analyzed using numerical simulation. Results show that: judging from the additional deformation index of the existing metro station floor, the initial support deformation of the new transfer passage, the surrounding rock mass plastic zone index, the maximum deformation value and the volume of surrounding rock mass plastic zone of Case 1 are both relatively small, therefore it is recommended to consider Case 1 as the preferred construction procedure.Key wordsmetro station; transfer passage; construction procedure; numerical simulation

     

/

返回文章
返回