Abstract:
Line and slope adjustment is an important part in the design of urban rail transit lines. By checking the clearance of the structural section, line and slope adjustment is carried out for the section with limit violation, so as to reduce or eliminate the limit violation and to provide guarantee for future track laying and equipment installation. Taking the engineering of Shanghai Rail Transit Line 15 for case study, the main process and method of line and slope adjustment design of circular tunnel are introduced.