Abstract:
In the process of metro construction, there are still many safety problems in the freezing method construction of connection passage. Taking the construction of 2# connection passage and pump room of Changjiang Road Station—Tayuan Road Station interval of Suzhou Rail Transit Line 5 as an example, the trend of surface settlement and deformation caused by the freezing method construction of connection passage in soft soil layer is analyzed according to monitoring data. Main conclusions are: the surface vertical displacement variation at the position of connection passage generally experiences five stages including drilling microchange, freezing uplift (frost heave), excavation undulation, thawing subsidence (thaw subsidence), and grouting stabilization; the surface maximum frost heave deformation of all sections perpendicular to central axis of connection passage is in the shape of a ‘convex semi-ellipse’, and the maximum thawing deformation is in V-shape; the surface deformation within a range of about 25 meters from the central axis of the connection passage is largely influenced by freezing method construction, and the impact beyond this range is relatively small.