杭州地铁1号线临平支线拆分的关键点

Key Points in Line Splitting for Hangzhou Metro Line 1 Linping Branch

  • 摘要:
    目的 地铁运营线路的拆分改造施工难度大,存在涉及专业多、新旧系统须兼容等问题,具有倒切风险大、夜间施工时间紧张、调试管理程序复杂等特点。为了在不停运、不提前结束运营的原则下完成拆分工作,有必要对拆分工作的关键点进行研究。
    方法 以杭州地铁1号线临平支线拆分项目为研究对象,从方案设计、工程实施、运营配合、行车组织等方面,探讨了线路拆分设计阶段所涉及的系统接口关系、新旧设备兼容性、倒切调试装置设计、废弃设备拆除等的关键点,以及拆分实施阶段所涉及的动车调试组织、软件配置管理、倒切柜管理、全系统倒切演练、系统割接、运营配合及移交等关键点,力求在完成拆分工作的同时,将运营风险降至最低。
    结果及结论 经过两年多的拆分改造,杭州地铁1号线已成功完成了临平支线拆分任务。线路拆分完成后,两条线路均实现了独立运营,各机电系统运行良好,满足运营指标要求。

     

    Abstract:
    Objective The splitting and renovation construction of metro operating lines is a highly complex task that involves multiple professional disciplines and challenges related to compatibility between new and existing systems. Such projects are characterized by high risks associated with system switchover, limited nighttime construction windows, and complex commissioning management procedures. To complete the splitting work without suspending or shortening metro operations, it is necessary to study the key points of the splitting process.
    Method Taking the split project of Hangzhou Metro Line 2 Linping Branch Line as the research object, key points are explored from the aspects including scheme design, project implementation, operational coordination, and train operation organization. Specifically, key points involved in line splitting design stage such as the system interface relationship, compatibility between new and old equipment, design of switchover commissioning devices, and dismantling of obsolete equipment are examined. Furthermore, critical aspects involved in the implementation stage, such as EMU train debugging organization, software configuration management, switchover cabinet management, full-system switchover rehearsals, system cutover, operational coordination, and handover procedures are investigated. The goal is to minimize operational risks while completing the split work.
    Result & Conclusion  After more than two years of splitting and renovation construction, the Linping Branch of Hangzhou Metro Line 1 has been successfully split. Following the completion of the project, both lines have achieved independent operation with all mechanical and electrical systems functioning properly, meeting the operational performance requirements.

     

/