平顶直墙暗挖车站密贴下穿既有地铁车站时空变形规律研究

Spatiotemporal Deformation Characteristics of Flat-roof Straight-wall Mined Station Closely Under-passing Existing Metro Stations

  • 摘要:
    目的 新建地铁车站密贴下穿既有线等近接工程中,既有地铁车站会在施工扰动下产生较大沉降,进而影响结构安全及线路运营安全。因此,应开展新建地铁车站施工对既有地铁车站结构扰动影响规律的相关研究。
    方法 以我国某新建地铁车站零距离暗挖下穿既有地铁车站为工程背景,简要介绍了工程概况、新建车站暗挖段设计方案,以及施工的关键施工技术和施工步序。采用有限元软件建立了新建车站的三维模型,对施工过程进行了仿真模拟,并与现场监测数据进行了对比验证。基于数值计算结果,对既有车站最终沉降、既有车站关键点变形特征进行了分析,并进一步探究了导洞施工工序对既有车站结构变形的影响规律。
    结果及结论  监测值与模拟值基本吻合,验证了所建数值模拟方法的准确性和可靠性。新建车站采用CRD(交叉中隔墙)法、多重预顶撑及注浆加固等复合式工艺,利用受力体系的合理转换有效地解决了沉降控制这一技术难题。新建暗挖车站施工对既有车站结构变形的影响主要以竖向位移为主,对水平向位移的影响较小。在空间维度上,新建暗挖车站施工对既有车站的沉降影响范围大约为暗挖车站宽度的2倍,且最不利危险点出现在既有车站中心轴线处。时间维度上,导洞6、导洞10、导洞14开挖后引起的既有车站关键点沉降增量较大,这些增量对最终沉降的贡献率分别为36.3%、30.3%、20.5%。

     

    Abstract:
    Objective In close-proximity projects such as newly built metro stations closely under-passing existing lines, the existing metro stations may experience significant settlement under construction disturbance, thereby affecting structural and line operational safety. Therefore, it is necessary to investigate the influencing law of construction disturbance from newly built metro stations on existing metro station structures.
    Method Taking a project in China where a newly built metro station closely under-passes an existing metro station by mining method at zero distance as the engineering background, the project overview, design scheme of the new station mined section, as well as key construction technologies and construction sequences are briefly introduced. A three-dimensional model of the new station is established using finite element software and the construction process is simulated. The results are verified by comparison with field monitoring data. Based on numerical calculation results, the final settlement of the existing station and the deformation characteristics at key points are analyzed, and the influence of pilot tunnel excavation sequences on the structural deformation of existing station is further investigated.
    Result & Conclusion  The monitoring results are generally in accordance with the simulated ones, thus verifying the accuracy and reliability of the numerical simulation method. By adopting composite construction techniques such as the CRD (cross diaphragm) method, multiple pre-support system, and grouting reinforcement, the technical challenge of settlement control is effectively solved through utilizing the rational transformation of the load-bearing system. Impacts of the new mined station construction on the existing station structural deformation are mainly characterized by the vertical displacement, with relatively minor influence on the horizontal displacement. In the spatial dimension, the settlement influence range of the new mined station on the existing station is approximately twice the width of the mined station, with the most unfavorable critical point located along the central axis of the existing station. In the temporal dimension, the excavation of pilot tunnels 6, 10, and 14 results in relatively large incremental settlement at key points of the existing station, which contributes 36.3%, 30.3%, and 20.5% to the final settlement respectively.

     

/

返回文章
返回