地铁无网车辆基地供电系统方案

Power Supply System Scheme for Catenaryless Metro Depots

  • 摘要:
    目的 地铁无网车辆基地的基础设施配置、检修工艺和调度方式均与传统车辆基地不同。在此影响下,其供电系统方案有待研究。对此,有必要研究地铁无网车辆基地的供电系统方案。
    方法 以昆明轨道交通5号线世博车辆基地为研究实例,按不同的无网配置模式对其相应供电方案的经济性、牵引能耗影响等方面进行了分析,从供电系统角度分析探讨了无网车辆基地的优缺点。
    结果及结论  不同的无网配置方案对车辆基地供电系统的设备影响和投资增减影响各不相同。总体来说,无网车辆基地能简化运营操作流程,提升车辆基地景观,降低杂散电流影响,同时也会提高对车载储能系统的要求,还会增加车辆基地有电区和无电区的隔离和管理内容,增大日常运营牵引能耗等。

     

    Abstract:
    Objective The infrastructure configuration, maintenance process, and dispatching mode of catenaryless metro depots differ from those of conventional depots. Under these influences, its power supply system scheme needs to be studied. Therefore, it is necessary to investigate the power supply system scheme for catenaryless metro depots.
    Method Taking the Shibo depot on Kunming Metro Line 5 as a case study, the corresponding power supply schemes under different catenaryless configuration modes are analyzed in terms of economic feasibility and traction energy consumption impacts. Furthermore, the advantages and disadvantages of catenaryless metro depots are explored from the perspective of power supply systems.
    Result & Conclusion Different catenaryless configuration schemes have different impacts on equipment and cause different investment fluctuations in depot power supply systems. Overall, catenaryless metro depots can simplify operational workflow, enhance the depot landscape, and reduce stray current impacts. However, they also impose higher requirements on onboard energy storage systems, increase isolation and management workload between electrified and non-electrified areas within the depot, and raise daily operational traction energy consumption.

     

/