富水含砂层矿山法地铁车站密贴下穿变形特性与施工参数研究

Study on Deformation Characteristics of Metro Station by Close-Proximity Under-Crossing and Construction Parameters by Mining Method in Water-Rich Sandy Strata

  • 摘要:
    目的 为保证密贴下穿施工既有车站的运营安全,需研究既有车站沉降变形特性及施工参数对其沉降的影响。
    方法 基于富水含砂地层中南京某新建地铁车站密贴下穿既有地铁车站工程,通过数值模拟与现场试验相结合的方法展开研究。首先,应用Plaxis 3D有限元软件建立了地铁车站下穿施工数值模型。然后,分析了新建矿山法施工中开挖步长(1.0 m、2.0 m、3.0 m)、初支厚度(0.3 m、0.4 m、0.5 m)、临时支撑拆除长度(5.0 m、10.0 m、全拆)对既有车站结构沉降的影响,得出了最优施工参数。最后,在模型分析基础上进行现场测试,通过布置监测点监测车站密贴下穿施工引起既有车站竖向位移的规律,验证了数值模型的准确性。
    结果及结论 既有结构竖向位移呈“V”形分布,距离既有车站中轴线1.1倍交叠段施工宽度范围内产生了显著扰动。减小开挖步长及拆撑长度可有效控制既有车站竖向位移,而初支厚度变化对结构竖向位移影响较小。与3 m开挖步长相比,1 m开挖步长引起的结构竖向位移最大值可减小63.6%。最后参照各项规范,结合施工空间及施工经济等因素提出了优化后的施工参数为:开挖步长(2.0 m)、初支厚度(0.3 m)、拆撑长度(5.0 m)。

     

    Abstract:
    Objective To ensure the operational safety of the existing station during the close-proximity under-crossing construction, it is necessary to study the settlement deformation characteristics of the station and the influence of construction parameters on the settlement.
    Method Based on the project of a newly-built metro station in Nanjing in close proxi-mity to and under-crossing an existing metro station in water-rich sandy strata, this study is carried out through combining numerical simulation and field tests. Firstly, a numerical model of the under-crossing construction is established using Plaxis 3D finite element software. Then, the effects of excavation step length (1.0 m, 2.0 m, 3.0 m), initial support thickness (0.3 m, 0.4 m, 0.5 m), and temporary support removal length (5.0 m, 10.0 m, or complete removal) on the existing station structural settlement during the new mining method construction are analyzed, and the optimal construction parameters are determined. Finally, field measurements are conducted based on the model analysis. Monitoring points are deployed to track the law of vertical displacement of the existing station induced by the closely under-crossing construction, verifying the accuracy of the numerical model.
    Result & Conclusion The vertical displacement of the existing structure shows a V-shaped distribution, and significant disturbance occurs within the range of 1.1 times the construction width of the overlapping section from the existing station central axis. Reducing the excavation step length and the temporary support removal length can effectively control the vertical displacement of the existing station, while the change in initial support thickness has a relatively small impact on the vertical displacement of the structure. Compared with an excavation step length of 3m, that of 1m can reduce the maximum vertical displacement of the structure by 63.6%. Finally, with reference to various specifications and considering factors such as construction space and construction economy, optimized construction parameters are proposed as follows: excavation step length (2.0 m), initial support thickness (0.3 m), and temporary support removal length (5.0 m).

     

/

返回文章
返回