富水软土地层盾构下坡掘进隧道管片错台控制技术研究与探讨

Research and Discussion on Control Technology of Segment Misalignment during Downward Shield Tunneling in Water-rich Soft Soil Strata

  • 摘要:
    目的 富水软土地层盾构下坡掘进隧道管片错台是盾构施工过程中的高风险因素,管片错台会严重影响施工安全和施工进度。目前相关研究尚未对富水软土地层盾构下坡掘进管片错台问题进行专门研究,因此需对此类地层管片错台影响因素进行针对性研究。
    方法 从理论层面分析了管片错台造成的漏水、漏浆情况和管片破损的严重后果,从错台控制标准、现场操作两个方面详细分析了造成管片错台的具体原因,为富水软土地层盾构下坡掘进隧道管片错台控制技术措施提供了理论支撑。
    结果及结论 采取所提出的管片错台控制技术措施后,案例隧道从管片开始拼装至脱出盾尾前各分块之间的高差控制在2 mm,相邻管片错台控制在4 mm;管片脱出盾尾之后至隧道成型,同环管片错台控制在12 mm以内,相邻管片错台控制在17 mm以内。研究结果表明,通过合理优化拼装点位,控制好掘进参数和同步注浆浆液,能够保障富水软土地层盾构下坡掘进隧道管片错台控制符合规范要求。

     

    Abstract:
    Objective Segment misalignment during downhill shield tunneling in water-rich soft soil strata is a high-risk factor in shield construction, as such misalignment can seriously affect construction safety and progress. At present, related studies have not specifically addressed segment misalignment in downhill shield tunneling under water-rich soft soil conditions; therefore, it is necessary to conduct targeted research on the influencing factors of segment misalignment in this type of stratum.
    Method From a theoretical perspective, the severe consequences of segment misalignment, including water leakage, grout leakage, and segment damage, are analyzed. The specific causes of segment misalignment are examined in detail from two aspects: misalignment control standards and on-site operations. This provides theoretical support for technical measures to control segment misalignment in downhill shield tunneling in water-rich soft soil stratum.
    Result & Conclusion  After adopting the proposed segment misalignment control measures, the elevation difference between individual segments from the start of segment assembly to shield tail clearance in the case tunnel is controlled within 2 mm, and the misalignment between adjacent segments is controlled within 4 mm. After the segments exited the shield tail and until tunnel formation, the misalignment within the same ring is controlled within 12 mm, and the misalignment between adjacent segments is controlled within 17 mm. The results indicate that by reasonably optimizing segment assembly positions and properly controlling excavation parameters and synchronous grouting materials, segment misalignment in downhill shield tunneling in water-rich soft soil strata can be controlled to meet specification requirements.

     

/

返回文章
返回