长江一级阶地富水砂层地铁隧道下穿既有车站的清障设计及施工方案

Obstacle Removal Design and Construction Scheme for Metro Tunnel Undercrossing Existing Stations in Water-Rich Sand Strata on the First Yangtze River Terrace

  • 摘要:
    目的 富水砂层新建地铁隧道下穿既有地铁车站时,会面临既有车站围护结构清障、既有车站变形影响控制、施工过程涌水涌砂等难题,因此,有必要对清障设计及施工方案进行研究。
    方法 基于武汉地铁12号线区间隧道下穿既有4号线园林路站工程,对工程立交关系与实施难点进行了分析。提出了长江一级阶地近接车站的围护清障设计与施工方案:首先在既有车站外侧设置清障井,随后将清障井开挖至盾构下穿深度进行水平冻结清障,回填清障井后再实施盾构下穿。采用数值模拟分析了清障井基坑开挖、冻胀融沉及盾构下穿对既有车站的影响,并进一步对比了数值计算结果与实际工程监测数据,验证了所提方案的有效性。
    结果及结论 数值模拟分析表明,清障井基坑开挖引起的4号线园林路站最大沉降量为3.2 mm,冻结加固引起的车站最大隆起值为2.5 mm,盾构下穿引起的车站最大沉降量为1.4 mm,均小于变形控制值。现场实测既有车站沉降变形数据与数值模拟分析结果规律相符,实测车站最大沉降量为3.5 mm,满足变形控制要求,设计施工方案安全可行。

     

    Abstract:
    Objective When a newly built metro tunnel in water-rich sand strata under-crosses an existing metro station, challenges such as obstacle removal from the existing station's retaining structure, deformation control of the existing station, and water and sand inrush during construction will be encountered. Therefore, it is necessary to study the design and construction schemes for obstacle removal.
    Method Based on the project of Wuhan Metro Line 12 interval tunnel under-crossing the existing Yuanlin Road Station of Metro Line 4, the spatial crossing relationship and construction difficulties are analyzed. A retaining structure obstacle removal design and construction scheme for stations adjacent to the first Yangtze River terrace is proposed as follows: first, an obstacle removal shaft is constructed outside the existing station; next, the shaft is excavated down to the shield under-crossing elevation for horizontal freezing and obstacle clearing; then, after backfilling the obstacle removal shaft, shield under-crossing is conducted. Numerical simulation is adopted to analyze the impacts of shaft foundation pit excavation, frost heave and thaw settlement, and shield under-crossing on the existing station. Furthermore, numerical calculation results are compared with field monitoring data to verify the effectiveness of the proposed scheme.
    Result & Conclusion Numerical simulation analysis shows that the maximum settlement of Yuanlin Road Station of Metro Line 4 induced by obstacle removal shaft excavation is 3.2 mm, the maximum station uplift caused by ground freezing reinforcement is 2.5 mm, and the maximum settlement induced by shield under-crossing is 1.4 mm, all lower than the allowable deformation limits. The field measured settlement deformation data of the existing station is consistent with the result from numerical simulation, with a maximum measured station settlement of 3.5 mm, meeting deformation control standards. Therefore, the proposed design and construction scheme is safe and feasible.

     

/

返回文章
返回